Initiated: Proposal is in progress and has not been submitted. The document is editable.
principalInvestigatorApproval: First level of approval. The document is no longer editable except for adding viewers to the Permissions page.UnitAdministrator: Second level of
proposalCoiAdministratorNotification: If the proposal is federally funded, it must be approved by a Conflict of Interest (COI) Administrator. The COI Administrator will ensure everyone listed on the Key Personnel page has a Foreign Partnerships in Research Disclosure on file before approving.
proposalSaiAdministratorNotification: If the project involves offsite or off-campus research activities and is being submitted to the NSF, the proposal’s attached safe and inclusive (SAI) plan must be approved by an SAI Administrator.
UnitAdministrator: Department level approval. This node will be skipped if there isn’t a Unit Admin listed on the lead unit.
OSPOfficeRouting: Proposal has reached the OSP for review.
holdForReturnedProposal: Proposal was returned for revisions. The document is editable and requires re-submission by the PI or other aggregator.
...
Initiated: Protocol is in progress and has not been submitted. The document is editable.
principalInvestigatorApproval: First level of approval. The document is no longer editable.
proposalCoiAdministratorNotification: If the proposal is federally funded, it must be approved by a Conflict of Interest (COI) Administrator. The COI Administrator will ensure everyone listed on the Key Personnel page has a Foreign Partnerships in Research Disclosure on file before approving.
proposalSaiAdministratorNotification: If the project involves offsite or off-campus research activities and is being submitted to the NSF, the proposal’s attached safe and inclusive (SAI) plan must be approved by an SAI Administrator.
UnitAdministrator: Second level of approval. This node will be skipped if there isn’t a Unit Admin listed for the lead unit.
IRBReview: Protocol has reached the OHRP for the final level of review.
...